Building Permit

Complex (7 working days) MEO 7 working days No Fees
Authorization to construct, alter, repair, or demolish a building in accordance with the National Building Code.

Who May Avail

Any person intending to construct, renovate, or demolish a structure.

Requirements

Accomplished application form
Lot title or proof of ownership
Signed building plans
Barangay clearance

Service Steps

1

Client

File application and plans at the Engineering Office.

Agency Action

Receive and evaluate the plans.

No fee 1 working day
2

Client

Await technical assessment.

Agency Action

Conduct plan review and site inspection.

No fee 3 working days
3

Client

Pay assessed fees.

Agency Action

Compute fees and issue the permit.

No fee 3 working days